DRIVERS can expect overnight road closures over the next month as a stretch of the A39 near St Audries is being repaired and upgraded.
Also in the news
Resurfacing project will see completion of A396 Cutcombe Hill engineering works
Man who urinated in Minehead church Holy water and damaged altar cross is sentenced
Campaigners want buses three days a week between Wiveliscombe and Wellington
Royal Marines from 40 Commando acquiring drone warfare skills in Arctic exercisesThe work, which starts on Monday September 19, is to tackle a long-running issue with cracking and subsidence along 800 metres.
The works have been planned to minimise disruption as much as possible and will be split into three phases:
* Drainage works from 7pm on Monday to 7am on Tuesday (September 19-20).
* Prep works with temporary traffic lights in place from Wednesday (September 21) until October 14.
* Geogrid construction and resurfacing with 7pm to 7am closures from October 10 to 20.